Site log April 6th, 2023

Jurnal de șantier 6 aprilie 2023 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log April 6th, 2023 In this interview from the site, Alexandru Niculescu, Site Manager h4l THE VILLAGE talks about the stage of the construction works for PHASE 1 and gives us details about the start of the foundation pouring for PHASE 2, as well as the completion period of […]

Site log – showroom – March 27th, 2023

Jurnal de santier showroom 27 martie 7

h4l THE VILLAGE SITE LOG Site log – showroom – March 27th, 2023 The construction and fitting out of the showroom in the h4l THE VILLAGE neighborhood is at a fairly advanced stage and is approaching completion at a fast pace.

Site log – PHASE 1 – March 27th, 2023

Jurnal de santier FAZA 1 27 martie 2023

h4l THE VILLAGE SITE LOG Site log – PHASE 1 – March 27th, 2023 We are making steady progress in the construction of houses with garden in PHASE 1 of h4l THE VILLAGE neighborhood. The images captured on the construction site speak for themselves:

Site log February 14, 2023 h4l THE VILLAGE

Jurnal de Șantier 14 februarie 2023, h4l THE VILLAGE, Pentru cei care își doresc mai mult

h4l THE VILLAGE SITE LOG Site log February 14, 2023 Alexandru Igor Hristenco, Senior Project Manager h4l, talks to us about the innovative solutions we use to achieve high energy efficiency and manage to reduce invoice costs by up to 40%, compared to the average in Romania.

Site log February 7, 2023 h4l THE VILLAGE

Jurnal de santier 7 februarie 2023

h4l THE VILLAGE SITE LOG Site log February 7, 2023 Alexandru Niculescu, Site Manager h4l THE VILLAGE tells us about the status of the works at the beginning of 2023, about what works are to come for PHASE 1 and PHASE 4, but also when construction will start for PHASE 2.

Site log h4l THE VILLAGE retrospective 2022

Jurnal de șantier 12 august 2022 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Retrospective of the year 2022 The h4l THE VILLAGE neighborhood construction work started in 2022 for PHASE 1 and PHASE 4 garden houses and TOWNHOUSES. Thus, for the houses with a garden, all the foundations were poured, and in the case of the TOWNHOUSES, the upper floors were poured.

Site log December 16, 2022 h4l THE VILLAGE

Jurnal de santier 16 decembrie 2022 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log December 16, 2022 Ionel Badea, Design Director, POPP & Asociații, talks to us in this interview about the resistance structure of garden houses and TOWNHOUSES within h4l THE VILLAGE. Here are the advantages, both functionally and aesthetically, of using the latest design techniques.

Site log 6 December 2022 h4l THE VILLAGE

Jurnal de șantier, 6 decembrie, h4l THE VILLAGE, Pentru cei care își doresc mai mult

h4l THE VILLAGE SITE LOG Site log 6 December 2022 Bogdan Vetrea, Project Manager h4l THE VILLAGE together with Engineer Mircea Sibana, Product Manager – XELLA Romania talk in this interview about the chosen solution in terms of masonry – XELLA Ytong.