Site log 6 December 2022 h4l THE VILLAGE

Jurnal de șantier, 6 decembrie, h4l THE VILLAGE, Pentru cei care își doresc mai mult

h4l THE VILLAGE SITE LOG Site log 6 December 2022 Innovative masonry solution Bogdan Vetrea, Project Manager h4l THE VILLAGE together with Engineer Mircea Sibana, Product Manager – XELLA Romania talk in this interview about the chosen solution in terms of masonry – XELLA Ytong. Site log 6 December 2022 h4l THE VILLAGE – video […]

Site log November 28, 2022 h4l THE VILLAGE

Jurnal de șantier, 28 noiembrie h4l THE VILLAGE, Pentru cei care își doresc mai mult, h4l

h4l THE VILLAGE SITE LOG Site log November 28, 2022 Bogdan Vetrea, Project Manager h4l THE VILLAGE together with Geo Bostan, Sales Director, Alukoenighstahl and Engineer Marian Vochin, Weru Klass Representative talk in this interview about the chosen solution in terms of carpentry – Schuco PVC carpentry. See here details about Schuco joinery This article […]

Site log November 21, 2022 h4l THE VILLAGE

Jurnal de șantier, 21 noiembrie h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log November 21, 2022 Site log – progress of works Construction works for PHASE 1 and PHASE 4 of the h4l THE VILLAGE neighborhood are at an advanced stage of construction. Alexandru Niculescu, Site Manager, tells us about the progress made on the site, about the advanced stage of […]

Site log, October 25, 2022 h4l THE VILLAGE

Jurnal de șantier, 25 octombrie, Pentru cei care își doresc mai mult, h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log, October 25, 2022 Construction work for PHASE 1 and PHASE 4 of h4l THE VILLAGE neighborhood is in full swing. Bogdan Vetrea, Project Manager, tells us about the solutions chosen to make the construction of houses with garden more efficient and how these are compartmentalized and sized for […]

Site log, October 20, 2022 h4l THE VILLAGE

Jurnal de șantier, 20 octombrie, Pentru cei care își doresc mai mult, h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log, October 20, 2022 Construction work for PHASE 1 and PHASE 4 of h4l THE VILLAGE neighborhood is in full swing. Bogdan Vetrea, Project Manager, tells us about how the works are progressing in the video below. You can also see what the construction site looks like and at […]

Site log, October 14, 2022 h4l THE VILLAGE

Evolutie Santier h4l THE VILLAGE -  14 octombrie 2022, case Bucuresti

h4l THE VILLAGE SITE LOG Site log, October 14, 2022 At the moment, the foundations for houses with garden and TOWNHOUSE have been poured for PHASE 1 and PHASE 4 of h4l THE VILLAGE neighborhood. Work is progressing on site with the casting of the top slabs and the showroom is in an advanced stage […]

Site log August 18, 2022 h4l THE VILLAGE

Jurnal de șantier 18 august 2022 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log August 18, 2022 Construction work for the houses with garden in PHASE 1 of h4l THE VILLAGE neighborhood is at the point where the foundations have almost been completed, with the next phase of development about to begin. This article also exists in Romanian here – Jurnal de […]

Site log August 12, 2022 h4l THE VILLAGE

Jurnal de șantier 12 august 2022 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log August 12, 2022 For PHASE 4 of the h4l THE VILLAGE neighborhood, the construction works are at a fairly advanced stage, as shown by the images captured on the construction site. Here, the construction of the upper floor of the houses with garden has already begun. This article […]

Site log June 10, 2022 h4l THE VILLAGE

Jurnal de șantier 10 iunie 2022 h4l THE VILLAGE

h4l THE VILLAGE SITE LOG Site log June 10, 2022 Construction work for the houses with garden and TOWNHOUSES within PHASE 1 of the h4l THE VILLAGE neighborhood continues with landscaping. Next comes the drawing of the foundations and the start of the actual works. This article also exists in Romanian here – Jurnal de […]

Site log October 22, 2021 h4l THE VILLAGE

Construcție drum acces, h4l THE VILLAGE, pentru cei care își doresc mai mult (6)

h4l THE VILLAGE SITE LOG Site log October 22, 2021 Status of construction work as of October 22, 2021 In October 2021 started the construction work for PHASE 1 and Phase 2 of the neighborhood that brings joy into life h4l THE VILLAGE. Thus, the work has begun with arranging the access road for the […]